Kitchen remodel change order template

A kitchen produces more change orders than any other room, because the client is choosing finishes, appliances and layout while the work is already running. This page sets out what the document has to say so the choices get approved instead of absorbed, with a worked example. The generator is free and needs no login.

No login, no email. The kitchen remodel template is preloaded and the PDF is yours to keep.

What a kitchen remodel change order must contain

These are the parts that decide whether the document settles an argument or starts one.

The change in the client's own selections
A 36 in. range instead of the 30 in. that was priced, a tile that goes to the ceiling instead of a 4 in. splash, a cabinet run that grows by a foot. Write it in the words the client used when they chose it, because that is the language they will recognise when they sign.
The reason, and what it replaces
Selection upgrade, allowance overrun, or something found after demo. Say which line of the original scope this replaces, so nobody pays twice and nobody claims the old price still applies.
Price per line, including what the change drags with it
A wider range means cabinet modifications, a countertop re-template, a different vent hood and possibly a gas line. Itemise the change and its consequences separately; the consequences are where kitchens lose money.
Allowances, and what happens when they are exceeded
If the contract carried an allowance for tile or countertops, show the allowance, the new selection's cost and the difference. A change order that converts an allowance overrun into an approved number is the single most useful document in a kitchen job.
The effect on lead times and the schedule
Cabinets, countertops and windows are long-lead items. If a selection change re-orders a cabinet or delays the template, put the new dates on the change order. The client needs to see that the delay is attached to their choice, not to your crew.
Written approval with a date
Signature, printed name, date, and a line stating that the rest of the contract is unchanged. Materials should not be ordered on a verbal yes.

The kitchen remodel traps that cost you money

The upgrade that arrives after the order
The client sees the cabinet sample in the room and wants the painted finish instead of the stained one. If the order has already gone in, the change is a cancellation fee plus a new lead time, not a colour choice. Price both.
Allowances nobody explained
A tile allowance of a certain amount per square foot is meaningless to a homeowner who has fallen in love with a tile at twice that. Show the arithmetic on the change order, or the overrun reads as an invented charge.
Concealed damage under a kitchen
Rot at the sink base, an unlevel floor under the new island, a wall that is not plumb behind the cabinets. All of it shows up after demo and all of it changes the install, not just the repair.
Appliance specs that move the trades
A dual-fuel range needs a gas line and a 240V circuit; a counter-depth fridge needs the cabinet run reworked. A spec change is rarely one trade's problem, and the change order is where the electrical and plumbing consequences get approved at the same time.

A filled-in kitchen remodel change order

Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.

Change order

Sample Renovations

Sample document — illustrative figures

Order
CO-006
Date
Jan 19, 2026
Client
Homeowner — full kitchen
Project
27 Cedar Lane
ItemQtyUnit priceTotal
Rework base cabinet run and fillers for 36 in. range, including new end panel1 ea$420.00$470.40
Extend tile backsplash to ceiling on range wall, set and grout48 sq ft$26.00$1,372.80
Install under-cabinet LED lighting, three runs, including driver and switch3 ea$145.00$478.50
Subtotal
$2,103.00
Markup
$218.70
Total due
$2,321.70

Reason for the change

The contract priced a 30 in. slide-in range with a 4 in. backsplash. The owner changed to a 36 in. dual-fuel range after the cabinets were released, so the base run, fillers and end panel have to be reworked, and asked for the backsplash to run to the ceiling on the range wall while the wall is open.

Effect on schedule

Cabinet rework adds five working days to the cabinet delivery. Countertop template moves after the range is on site.

Client signature

Printed name

Date

Contractor signature

Printed name

Date

Start from this template

When to issue one

  • A selection comes in over its allowance, or the client upgrades after the material order has been released.
  • The layout changes after demo — an island added, a wall removed, a cabinet run extended.
  • Demo exposes rot, an unlevel floor or out-of-plumb walls that change how the cabinets install.
  • An appliance specification changes and pulls electrical, plumbing or ventilation work with it.

Questions contractors ask

Should an allowance overrun go on a change order?
Yes, and before the material is ordered. An allowance is a budget, not a price, and the change order is what converts the difference into an approved number. Doing it at selection time means the client is choosing to spend the money rather than reading about it at the end.
What if the client changes their mind again after signing?
Write a new change order. Editing a signed one destroys the record of what was approved and when, which is the only thing the document is for. Number them in sequence — CO-006, CO-007 — so the job file reads in order.
Does this kitchen change order template cost anything?
No. The generator is free, needs no login, and downloads a PDF you can print or email. Sending, e-signature and payment collection are planned for the paid plans and are not launched yet.

Put your name and price on it in two minutes

The generator opens with the kitchen remodel line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.