Tile change order template

Tile work is priced on assumptions about the floor, the pattern and the material, and every one of those can change after the quote is signed. This page covers what the change order has to record so the extra prep, cuts and waste get paid for. The generator is free and needs no login — pick Tile & flooring and edit the lines.

No login, no email. The tile template is preloaded and the PDF is yours to keep.

What a tile change order must contain

These are the parts that decide whether the document settles an argument or starts one.

The change, by area and pattern
220 sq ft of 12 x 24 porcelain set herringbone instead of straight, floor prep in the kitchen and hall, trim at two doorways. Area, material and pattern in the description, because all three drive the price.
Why it changed, with the condition that forced it
The owner changed the pattern after the material was ordered, or the floor failed the flatness check before any tile went down. State the measurement and where you took it; a number the client can check is hard to argue with.
Prep as its own line
Self-levelling, crack isolation membrane, cement board, a deflection fix. Prep is the part clients most often assume was included, and it is usually the largest single line in the change order. Keep it separate from the tile so the two are never confused.
Waste, cuts and trim
A pattern change changes the waste factor and the number of cuts per edge. Show the square footage ordered against the square footage installed, and price the trim and thresholds that go with the new layout.
The schedule, including cure time
Thin-set and grout need time before heavy traffic or the next trade. Put those days on the change order so a slow start to the next phase is not read as your delay.
Written approval with a date
Before the material is ordered, not after it is stacked in the garage.

The tile traps that cost you money

Substrate that fails the flatness check
A floor can look fine and still be out of tolerance over a long straightedge, or spring underfoot. Once you set tile on it, every defect is your defect. Measure, write the number down, and price the levelling before the first bag is mixed.
Deflection and joist structure
A floor that meets the flatness tolerance can still move too much for a stone or a large-format porcelain. If the structure needs work, that is a framing and prep cost the client has never considered.
The pattern change after the order
Herringbone or a chevron layout changes the cutting, the waste and sometimes the tile itself. If the material is already on site, the extra is real money and the client needs to see it as a consequence of their choice.
Heated floor or membrane added late
An uncoupling membrane or a heat mat changes the build-up, the finished floor height, the door undercut and the schedule. Late additions ripple through the room, and the change order is where the ripple is priced.

A filled-in tile change order

Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.

Change order

Sample Tile Works

Sample document — illustrative figures

Order
CO-005
Date
May 12, 2026
Client
Homeowner — kitchen and hall floor
Project
301 Palmer Rd.
ItemQtyUnit priceTotal
Self-levelling underlayment over 220 sq ft, 1/8 in. average build220 sq ft$3.25$786.50
Install 12 x 24 porcelain floor tile in herringbone, including thin-set, grout and sealer220 sq ft$14.00$3,449.60
Install Schluter edge trim at two doorways18 lf$12.00$216.00
Subtotal
$4,011.00
Markup
$441.10
Total due
$4,452.10

Reason for the change

The contract priced a straight-set floor over existing subfloor. The owner changed to a herringbone layout after the tile was ordered, which adds a cut at almost every edge and needs more material for waste. The floor also measured about 3/8 in. out of flatness over a 10 ft straightedge, so it has to be levelled before any tile goes down.

Effect on schedule

Levelling needs a day to cure before tile starts. Floor moves two working days; the cabinet reinstall moves with it.

Client signature

Printed name

Date

Contractor signature

Printed name

Date

Start from this template

When to issue one

  • The pattern, tile size or material changes after the quote — especially after the material order has been released.
  • The substrate fails a flatness or deflection check, or needs prep that the quote assumed was already done.
  • The client adds a heated floor, an uncoupling membrane or a different trim detail after the build-up was agreed.
  • The layout changes after demo because a wall is out of square or a cabinet run moved.

Questions contractors ask

Should the waste factor be on the tile change order?
Show it. State the square footage ordered against the square footage installed and let the client see why a herringbone layout needs more material than a straight set. Waste that is explained is accepted; waste that appears on an invoice is disputed.
What if the floor is out of flatness after I have quoted?
Stop and issue a change order before you set any tile. A floor that is out of tolerance is a substrate problem, and setting over it makes every defect yours. Price the levelling or the membrane as its own line with the measurement that required it.
Does this tile change order template cost anything?
No. The generator is free, has no login and exports a PDF you keep. Nothing you enter leaves your browser, and the sending, e-signature and payment features belong to paid plans that have not launched yet.

Put your name and price on it in two minutes

The generator opens with the tile line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.