Change order markup percentage

Markup is the amount added to your cost to arrive at the price on the change order. This page is about the mechanics: where it is applied, how it is shown to the client, and what happens when it is hidden inside the unit price. It deliberately gives no “typical” percentage, because there is no single number anyone can source, and an invented one is worse than none.

Free, no login, and the PDF is yours to keep. Sending it to the client for an e-signature is $29/month.

Markup and margin are not the same number

This is the arithmetic that catches people out, and it is worth doing once on paper.

Your cost for the change is $1,000.

  • Add 20% markup: $1,000 × 1.20 = $1,200 price.
  • Margin on that price is $200 ÷ $1,200 = 16.7%, not 20%.
  • To end up with a 20% margin, divide instead of multiplying: $1,000 ÷ 0.80 = $1,250 price.

Which one you use is your call, but the column on the change order has to say which one it is. A column headed “markup %” that is really margin is a number nobody can check.

Where the markup goes

On each line
Every row carries its own quantity, unit price and markup, and the total is the sum of the rows. It is the most work to fill in and the least work to defend: the client sees where the money went, and a question about one row stays a question about one row.
On the job total
Line items at cost, then a single markup line under the subtotal. Simple, fast on a phone, and one number for the client to argue with instead of five. It also hides which part of the work is carrying the margin, which is fine when you know.
Inside the unit price
No markup column at all: the price is $145 each and the client cannot tell whether that is material, labour or your margin. This is the version that starts the argument — the moment they find a cheaper unit price at the supply house, every line on the document looks inflated, and you are defending your whole price instead of one number.

Zero markup is a legitimate number

Some costs on a change order should not carry markup: a permit fee, an engineer's review the client is paying at cost, a subcontractor's invoice the client has already seen. Put them on the document with a markup of 0 and say so. A pass-through line shown as a pass-through buys credibility for the lines that are not.

The same goes the other way. A small change carries the same truck roll, the same phone call and the same risk of an unknown condition as a large one, so a percentage that works on a $20,000 change can leave nothing on a $300 one. That is a judgement about your own overhead, and it is the one number on this page we cannot give you.

How the generator shows it

Every line item in the free change order generator has its own markup field, and the totals below the rows show subtotal, markup and total as three separate numbers. The PDF prints them the same way, so the client reads a document that separates cost from markup instead of a single figure they have to take on trust.

If the change is trade-specific, start from that trade's page — electrical, plumbing, painting or one of the others — and the line items arrive with the markup column already in place. For the rest of the document, read how to write a change order.

Free to build, $29 a month to send

The generator, the markup column, the live totals and the PDF are free with no login. Sending the finished order to the client for an e-signature — with the timestamp and the signed PDF kept as your record — is Pro at $29/month or $290/year.

Put your own number on it

Open the generator, add the line items and set the markup on each row. The totals update as you type, and the PDF prints cost and markup as separate lines.