Painting change order template
Painting is priced before anyone touches a wall, and almost everything that moves the number is either behind the paint or in the client's final colour choice. This page covers what the change order has to say to get that approved, with a worked example. The generator is free and needs no login — pick Painting, edit the lines and download the PDF.
No login, no email. The painting template is preloaded and the PDF is yours to keep.
What a painting change order must contain
These are the parts that decide whether the document settles an argument or starts one.
- Surface and area, not “the house”
- Walls, ceilings, trim, doors, the stairwell — with square feet or a room count you both mean. “Repaint interior” is a contract line. The change order is where “three bedrooms and the hall ceiling” gets priced, so name the rooms and the surfaces.
- The prep that was not in the price
- Wallpaper that comes off taking the drywall's face with it, failing plaster, a water stain that has to be sealed before it can be coated, caulk and fill at every joint. Prep is the line that decides whether a paint job makes money, and it is invisible on the quote until it is written down.
- Coats and product
- Two coats or three, primer plus two, a specific sheen or a specific product line. A scrubbable finish and a colour that needs an extra coat are both cost, and both belong on the document rather than absorbed into the day.
- The colour, and the date it was confirmed
- Colour name, code, and the date the client confirmed it. A colour chosen after the walls were coated is a re-coat at your cost unless the date on the document shows when it was agreed.
- Protection and access
- Furniture moved and covered, floors masked, a stairwell that needs staging, a room that has to be emptied before anything can be sprayed. These are hours, and hours are the quote.
- Approval with a date, and the amendment sentence
- Printed name, signature, date, and one line saying this amends the signed scope of work and the rest of the contract stands. On a painting job the date also fixes which colour was approved, which is the argument you are most likely to have.
The painting traps that cost you money
- Lead-safe work in older housing
- In the US, work that disturbs paint in pre-1978 housing falls under the EPA's Renovation, Repair and Painting rule, and containment, cleaning and disposal are real cost. Where the original price did not include them, they belong on the change order with the reason named, not absorbed into the labour.
- Each colour change is a coat
- A client who moves from charcoal to white after the first coat has added a coat, not asked a favour. Price the coat and say what it covers, because the alternative is doing it free and resenting the job.
- The trim that appears
- “While you're here, can you do the doors and the baseboards?” is the most common painting change and the easiest one to lose money on. Measure it, price it, or decline in writing — the middle option is what costs you.
- Drywall repair is not painting
- If the wall has to be patched and sanded before it can be coated, that is either a line item on this change order or a sentence saying the client is arranging it. Silence here becomes your weekend.
Where this crosses another trade
A painting change often drags work from another trade onto the same order. When it does, the other page covers what that half of the document has to say: general contractor change order template.
A filled-in painting change order
Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.
Change order
Sample Painting Co.
Sample document — illustrative figures
- Order
- CO-003
- Date
- May 19, 2026
- Client
- Homeowner — three bedrooms and hall repaint
- Project
- 22 Alder Court
| Item | Qty | Unit price | Markup | Total |
|---|---|---|---|---|
| Remove wallpaper in hall, 180 sq ft, skim-coat to a paintable surface | 180 sq ft | $4.50 | 10% | $891.00 |
| Seal water stain at hall ceiling with stain-blocking primer | 40 sq ft | $3.25 | 10% | $143.00 |
| Additional coat on three bedroom walls after colour change, charcoal to white | 1 ea | $420.00 | 0% | $420.00 |
| Paint six interior doors and frames, two coats | 6 ea | $85.00 | 12% | $571.20 |
- Subtotal
- $1,870.00
- Markup
- $155.20
- Total due
- $2,025.20
Reason for the change
The hall wallpaper was priced as a straight repaint over it, but removing it took the face of the drywall, so the wall needs a skim coat and sanding before it can be painted. The owners also changed the bedroom colour from charcoal to white after the first coat, which needs one more coat to cover.
Effect on schedule
Two extra working days: one for the skim coat to dry and be sanded, one for the additional coat. The rest of the interior stays on the original schedule.
Client signature
Printed name
Date
Contractor signature
Printed name
Date
When to issue one
- The walls reveal damage, failing plaster or wallpaper removal that nobody priced once the room is empty.
- The client changes colour or product after the price was set, and covering it takes another coat.
- The scope grows by rooms, ceilings, doors or trim that were not in the original price.
- The work disturbs paint in older housing and needs containment, cleaning and disposal that the price did not include.
Questions contractors ask
- Is a colour change a change order?
- It is when it adds a coat, a primer or a different product after the price was set. A colour change on the same number of coats is usually just a selection. The moment it costs an extra coat, it is scope, and it needs a price and a date on it.
- Does an older house change the price of a repaint?
- It can. In the US, disturbing paint in pre-1978 housing falls under the EPA's Renovation, Repair and Painting rule, and where it applies the containment, cleaning and disposal are costed work. Check what your jurisdiction requires, then put it on the change order as its own line with the reason.
- Is this painting change order template free?
- It is free and needs no login. Fill it in, check the preview and download the PDF. Nothing you type leaves your browser. Sending it to the client for e-signature is the paid part — $29/month or $290/year, cancel any time.
Put your name and price on it in two minutes
The generator opens with the painting line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.
Other trade templates
- Electrical change order templateCircuits, panel capacity, and who patches the wall afterwards.
- Plumbing change order templateConcealed pipe, stub-outs, and the wall you have to open.
- Kitchen remodel change order templateAllowances, appliances, and the layout the client changed.
- Bathroom remodel change order templateWet subfloor, niches and benches, and code-triggered work.
- Tile change order templateSubstrate, pattern, waste, and the prep under the tile.
- Roofing change order templateDecking, flashing, ice barrier, and the second layer.
- HVAC change order templateSizing, line sets, and the duct that cannot carry the air.
- General contractor change order templateAllowances, hidden conditions, and the selections that moved.
- Drywall change order templateFinish levels, texture matches, and what is behind the board.
- Free change order generatorAll nine trade templates, line items, markup and a PDF.