Drywall change order template

Drywall is priced on an assumption about how much board there is and how smooth it has to end up, and both of those move once the walls are open. This page covers what a drywall change order has to record so the extra board, the higher finish level and the texture match get paid for, with a worked example. The generator is free and needs no login: there is no separate drywall template in it, so this page starts you on General remodeling, which carries the hanging, taping and finishing lines.

No login, no email. The general remodeling template is preloaded and the PDF is yours to keep.

What a drywall change order must contain

These are the parts that decide whether the document settles an argument or starts one.

The area, in square feet and rooms
96 sq ft at the hall ceiling, 42 sq ft for a new closet partition, 18 lf of corner bead. Board is bought and finished by area, so the change order should be priced by area. “Drywall repairs” is the description that lets a client assume the patch was already in the contract.
The finish level, named
Level 3, 4 or 5 — or, if you do not use the levels, the words that mean the same thing to you: tape and one coat, tape and three coats sanded, a full skim. The level is the difference between a wall that looks fine under a window and one that shows every joint under a raking light, and it is the number the price depends on.
What was behind the board, and when you found it
Water staining along two joists, a bay that had been furred out, insulation missing from a wall, knob-and-tube wiring inside the cavity. Dated findings tie the extra work to the condition of the building rather than to your estimate.
Texture, and who owns the match
If the existing ceiling or wall has a texture, say what it is and whether you are matching it, skimming it out, or leaving it to someone else. A match on a small patch in a heavy texture is not something anyone can promise, and the change order is where that is said before the first coat.
The board type the assembly needs
Moisture-resistant in a bathroom, fire-rated where the assembly is rated, cement board behind tile, and who is responsible for the rating being maintained. Substituting the board that was priced for a different one is a cost, and it is a code question, not a preference.
Where the finish stops, and the approval
Say whether the work stops at a sanded, paint-ready surface or includes primer and paint, then get the client's signature and date under the total. The paint boundary is the most common misunderstanding on a drywall change and the cheapest one to write down.

The drywall traps that cost you money

Matching a texture you cannot match
An orange-peel or hand-troweled ceiling will not blend invisibly at a patch, and under a raking light the repair will show however well it is done. The honest options are skim the whole surface or accept a visible patch, and the client should be choosing between them on a priced document rather than discovering the seam at handover.
Plaster and lath is not drywall
An older wall has a plaster finish on wood lath, and it takes a different repair, a longer dry time and often a bonding agent. If the original price assumed board, the change order is where the difference is named — it is one of the few changes a client can see for themselves once it is explained.
The level of finish nobody specified
A wall finished to Level 4 and painted in a sheen, under a window or beside a stair light, shows joints that were always there. That is not a defect, it is the level that was priced — unless the document promised smooth, in which case it is your cost to fix. Write the level down.
Board that was already damaged when you arrived
Soft board under a bathroom, a ceiling that has been wet and dried twice, board that crumbles at the corner when you cut it. Photograph it before you remove it and price the replacement as its own line, so the water damage is not read as your workmanship.

Where this crosses another trade

A drywall change often drags work from another trade onto the same order. When it does, the other page covers what that half of the document has to say: general contractor change order template and painting change order template.

A filled-in drywall change order

Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.

Change order

Sample Drywall & Finish

Sample document — illustrative figures

Order
CO-002
Date
Mar 24, 2026
Client
Homeowner — hall ceiling repair
Project
63 Warren St.
ItemQtyUnit priceTotal
Remove and replace 1/2 in. drywall at hall ceiling, water damage from bath above96 sq ft$4.25$448.80
Level 4 finish: tape, three coats, sand to paint-ready96 sq ft$2.75$290.40
Skim remaining ceiling to a smooth finish to match new board140 sq ft$3.10$477.40
Haul away debris1 ea$120.00$120.00
Subtotal
$1,226.00
Markup
$110.60
Total due
$1,336.60

Reason for the change

The hall ceiling was priced as a patch of about 20 sq ft where the stain was showing. When the damaged board came down, the leak from the bathroom above had tracked along two joists, so 96 sq ft of board has to be replaced. The rest of the ceiling carries a heavy texture that cannot be matched at a patch, so the whole ceiling is skimmed to a smooth finish instead.

Effect on schedule

Board, tape and coats add two working days, plus one for the skim to dry before sanding. The paint moves three working days; nothing else on the schedule changes.

Client signature

Printed name

Date

Contractor signature

Printed name

Date

Start from this template

When to issue one

  • The client adds a wall, opening, soffit or closet after the board was priced and hung.
  • Demo or a repair reveals water damage, rot or failed board that was not visible when the work was quoted.
  • The finish level or the texture requirement goes up — a raking light, a gloss paint, a wall that has to be smooth.
  • An assembly needs a fire-rated or moisture-resistant board that the original price did not carry.

Questions contractors ask

Is a drywall repair a change order?
It is when it is concealed damage or added scope: water staining found after demo, a wall that has to come out for a change the client asked for, a finish level that was never priced. It is not when it is a defect in your own work — that is a callback, and putting it on a change order tells the client you think they should pay for your mistake.
Does the drywall change order include paint?
Only if it says so. Finishing normally stops at a sanded, paint-ready surface, and priming and painting are either a separate line on the same document or a sentence saying the client is arranging them. Leaving the boundary unspoken is how a drywall change turns into a free paint job.
Is this drywall change order template free?
It is free and needs no login. Fill it in, check the preview and download the PDF. Nothing you type leaves your browser. Sending it to the client for e-signature is the paid part — $29/month or $290/year, cancel any time.

Put your name and price on it in two minutes

The generator opens with the general remodeling line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.