Construction change order template
A construction change order template for residential work: the fields that decide whether the document settles an argument or starts one, a filled-in example with real line items, and a free generator that exports the PDF with no login. It is written for remodelers and small general contractors, not for a commercial job with a formal change-order process.
Free, no login, and the PDF is yours to keep. Sending it to the client for an e-signature is $29/month.
What the template covers
Six fields. Each one answers a question the client will ask later, which is the only test that matters for whether it belongs on the page.
- Who, what job, which order number
- Your business, the client, the project address, a change order number and a date. Two change orders on one job with no numbers are two documents nobody can put in order afterwards.
- The change, in quantities and locations
- A 12 foot opening, six sheets of sheathing, 42 linear feet of line set. Quantities are what let a client accept or question one line instead of the whole total.
- Why it changed, and who asked
- An owner request with the date, a condition found after demo, an inspector's correction. Name the trigger. Without it the change reads as an overrun, and overruns get argued.
- Line items with a visible markup column
- Quantity, unit, unit price, markup, row total, then subtotal, markup and total. Markup shown separately is a number the client can see and accept; markup buried in the unit price is a number they discover later.
- The effect on the schedule
- Which date moves and by how many working days. Two lines of honesty here prevent the most expensive conversation on a remodel.
- Signature, printed name, date, and the amendment sentence
- The signature block plus one line saying this amends the signed scope of work and the rest of the contract stands. That sentence is the difference between an amendment and a note.
The template, filled in
A wall comes out of a whole-home remodel. The owners asked on 14 April, the plan showed it as non-bearing, and the engineer's review said it needs a header. This is what the three lines and the two notes look like on the page.
| Item | Qty | Unit price | Markup | Total |
|---|---|---|---|---|
| Remove 12 lf wall between kitchen and dining room, install LVL header and posts | 1 ea | $1,450.00 | 12% | $1,624.00 |
| Reframe and patch ceiling at removed wall, ready for paint | 1 ea | $480.00 | 10% | $528.00 |
| Relocate two switch legs and add receptacle on the new dining room wall | 1 ea | $260.00 | 15% | $299.00 |
- Subtotal
- $2,190.00
- Markup
- $261.00
- Total
- $2,451.00
Reason for the change
The owners asked on 14 April to open the kitchen to the dining room. The wall was drawn as non-bearing and the engineer's review confirmed it can carry the load only with a new header, so the change is the header, the framing and the electrical moved out of the removed wall.
Effect on schedule
Two working days for the framing and the inspection, one for the patch. The cabinet install moves by three working days; nothing else changes.
Which template to start from
The generator carries nine trade templates. Each one preloads the line items that trade actually bills, so you edit rather than type from scratch: general remodeling, kitchen, bathroom, electrical, plumbing, tile and flooring, roofing, painting and HVAC. If the change crosses two trades, the general template is the right one — one document, both trades on it.
For the judgement calls rather than the fields, read how to write a change order and how markup is applied and shown. If you just want the blank page, that is the contractor change order form.
Free to fill in, $29 a month to send
The template, the line items, the markup column, the live totals and the one-page PDF are free, with no login and no email. Sending the finished order to the client's phone, their e-signature with a timestamp, the signed PDF and photo attachments are Pro — $29/month or $290/year. A free account saves your orders, and nothing is charged until you decide to send one.
Two minutes to your own version of this
Open the generator with the general remodeling template loaded, edit the three lines to match your change, and download the PDF.