How to write a change order

Seven steps, in the order they matter. A change order is not a long document — one page is normally enough — but each of these parts answers a question the client will ask months later, which is the only test for whether it belongs on the page.

Free, no login, and the PDF is yours to keep. Sending it to the client for an e-signature is $29/month.

The seven steps

  1. 01

    Describe the change in the client's words

    The opening they asked for, the tile they picked, the circuit the inspector wants. Add the location and the quantity, because a description without a quantity is a price the client cannot check.

  2. 02

    Say why it changed and who asked

    Owner request on 14 April. A wall that came open. A correction notice from the inspector. The trigger and the date are what make this an approved change instead of a cost overrun in the client's memory.

  3. 03

    Itemise the price

    One row per piece of work: quantity, unit, unit price. A lump sum invites a counter-offer on the whole number; rows invite a question about one row, which is a cheaper conversation to have.

  4. 04

    Show the markup as its own column

    Cost and markup separated, then subtotal, markup and total. See how change order markup is applied and why hiding it in the unit price starts an argument.

    How change order markup works

  5. 05

    State the effect on the schedule

    Which date moves and by how many working days, and what waits on what. Two lines here prevent the most expensive conversation on the job.

  6. 06

    Reference the original contract

    One sentence: this change order amends the signed scope of work and the rest of the contract stands. That is what makes it an amendment rather than a suggestion.

  7. 07

    Get the signature and the date

    Printed name, signature, date — from everyone named on the contract. The date fixes when the price was agreed and when the extra work started.

An example

A homeowner asks, on a Tuesday, for the opening between the kitchen and the dining room to be widened. The wall was in the contract; the extra width was not. On one page:

The change
Widen the kitchen-to-dining-room opening from 5 ft to 12 ft: remove the existing wall, install an LVL header and posts, reframe and patch, relocate two switch legs.
Why
Owners asked on 14 April. The plan showed the wall as non-bearing; the engineer's review confirmed the load needs a header.
The price
Header and framing $1,624 · patch and sand $528 · electrical $299 · engineer at cost $350. Subtotal $2,540, markup $261, total $2,801.
Schedule and signature
Cabinet install moves three working days. Signed by both owners, dated 21 April, with the line saying the rest of the contract stands.

That is the whole document. Nothing on it is a legal formula, and nothing on it is decoration — every line exists to answer a question later.

Change order or variation order?

The same document, under two names. In the US and Canada it is a change order. In the UK, Australia and New Zealand — and in standard forms such as JCT — it is usually a variation or a variation order. Both record a priced, dated change to a scope that was already signed, and every step above applies to either. If you are writing for a UK client, use their word: “variation order” is what they will look for on the page.

Two related documents are worth keeping separate. A field order or change directive is the instruction to proceed before the price is agreed — useful when the work cannot wait, and dangerous if it is never followed by the priced document. An allowance reconciliation is not a change at all: it settles a selection that was already paid for inside the contract.

What to leave off the page

  • Blame. “Client failed to decide” wins an argument and loses the next job.
  • Adjectives. “Extensive”, “substantial” and “major” all mean nothing when the price is questioned.
  • Lump sums with no rows behind them.
  • Promises about future work, discounts or timelines that are not part of this change.

Then start from a page that already has the fields: the contractor change order form, the construction change order template, or a trade page such as general remodeling or kitchen.

Free to write, $29 a month to send

Writing it and downloading the PDF costs nothing and needs no login. Sending the finished order to the client's phone for an e-signature, with the timestamp and the signed PDF kept as your record, is Pro — $29/month or $290/year.

Write the one you owe somebody today

The generator opens with the line items already in it, the markup column, the reason box and the signature block. Edit, download, hand it over.