HVAC change order template
An HVAC change order is where the equipment swap, the new line set and the duct nobody priced get approved — before the truck is unloaded, not after the old condenser is already on the lawn. This page sets out what the document has to say, with a worked example. The generator is free and needs no login: pick HVAC, edit the lines and download the PDF.
No login, no email. The hvac template is preloaded and the PDF is yours to keep.
What a hvac change order must contain
These are the parts that decide whether the document settles an argument or starts one.
- The equipment, by size and model
- A 3.5 ton condenser with the matching air handler, and the model numbers written out. The client will compare the number on the quote with the number on the crate, so give them both. “New AC unit” is a description that fits every price from the cheapest to the largest.
- Why the size changed, and what measured it
- A room-by-room load calculation, a manual J, a return that cannot carry the airflow — whatever produced the number. If the new equipment is a different size from what came out, say which measurement drove the change, because the client hears “you sold me something bigger” unless the document answers it first.
- The parts a swap actually needs
- Line set, pad, whip, disconnect, condensate pump and float switch, thermostat, plenum transition, permit. These lines are what turn a two-hour changeout into a two-day job, and they are the ones that go missing from a verbal quote on the driveway.
- Duct work, measured
- A return enlarged to 20 x 25, a trunk re-run to reach a converted garage, joints sealed and insulated. Airflow is a measurement, so price it as one — square feet, linear feet, or a count of drops — rather than as “duct modifications”.
- The days the house has no heating or cooling
- A changeout in July means a night without cooling if the line set has to be replaced, and a furnace swap in January means the same in reverse. Name the day the system goes down and the day it comes back, because that is the part of the change the household actually feels.
- Approval with a date, and the amendment sentence
- Printed name, signature, date, and one line saying this amends the signed scope of work and the rest of the contract stands. The date is what fixes when the price was agreed and when the extra work started.
The hvac traps that cost you money
- Equipment lead time and price movement
- Equipment is ordered, not picked off a shelf, and the price on a quote can move before the unit lands. If the price on the change order expires, write the date it expires. What you must not do is carry a rise silently and raise it at the final invoice.
- The refrigerant the new unit uses
- New equipment does not always use the refrigerant the old system did, and that changes the line set, the oil and the pressure test. Name the refrigerant and the reason the line set is being replaced, because reusing a line set built for the old system is not something to do quietly.
- Duct that cannot carry the new airflow
- A larger unit on the same undersized duct pushes more air through a smaller hole: noise, rooms that still will not cool, and a callback that is yours. If the duct has to change to make the new equipment work, that is scope, and it belongs on the document.
- The circuit nobody looked at
- A new condenser may need a different breaker, a disconnect within sight of the unit, and protection the code now requires. That is an electrician's line item and it goes on this change order, not discovered on install day with the unit on the pad.
Where this crosses another trade
A hvac change often drags work from another trade onto the same order. When it does, the other page covers what that half of the document has to say: electrical change order template.
A filled-in hvac change order
Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.
Change order
Sample Heating & Air
Sample document — illustrative figures
- Order
- CO-004
- Date
- Jul 8, 2026
- Client
- Homeowner — upstairs bedrooms not cooling
- Project
- 77 Cedar Bend
| Item | Qty | Unit price | Markup | Total |
|---|---|---|---|---|
| Replace 3 ton condenser and coil with 3.5 ton, 14.3 SEER2, matching air handler | 1 ea | $3,850.00 | 12% | $4,312.00 |
| New line set, 3/8 in. and 3/4 in., 42 lf, with pad and whip | 42 lf | $11.00 | 10% | $508.20 |
| Enlarge return air drop to 20 x 25 and seal trunk joints | 1 ea | $640.00 | 15% | $736.00 |
| Dedicated 30A circuit and disconnect for new condenser | 1 ea | $385.00 | 10% | $423.50 |
- Subtotal
- $5,337.00
- Markup
- $642.70
- Total due
- $5,979.70
Reason for the change
The upstairs bedrooms never cooled on the original 3 ton system. A room-by-room load calculation puts the second floor at 3.5 tons on a 100F day, and the existing return drop is too small for the airflow the larger unit needs. The condenser also needs a dedicated 30A circuit that the original scope did not include.
Effect on schedule
Equipment is on site; the changeout is one working day. The return work and the circuit happen the same day, so the house is without cooling for one afternoon. If the existing line set cannot be reused, add one more day.
Client signature
Printed name
Date
Contractor signature
Printed name
Date
When to issue one
- The equipment that failed is not the size the load calculation calls for, and the difference is real money.
- The line set, pad, disconnect or condensate safety cannot be reused and was not in the original price.
- The duct cannot carry the airflow of the new equipment, so the return or trunk has to change to make the install work.
- The inspector or the code requires a circuit, a disconnect or a safety device that nobody priced.
Questions contractors ask
- Is a bigger system the answer to a room that will not cool?
- Not always, and the change order is where that honesty gets paid for. An undersized return, an unbalanced duct run or a room with a lot of west-facing glass can all leave a room hot on equipment that is already the right size. If the measurement says the fix is duct work rather than tonnage, price the duct work.
- Does replacing a system need a permit?
- Requirements vary by jurisdiction, so check the one you are working in. Where a permit and an inspection are required, put them on the change order as their own line with the inspection named, so the client sees the cost of doing it properly rather than finding it in the final invoice.
- Is this HVAC change order template free?
- It is free and needs no login. Fill it in, check the preview, download the PDF. Nothing you type leaves your browser. Sending it to the client for e-signature is the paid part — $29/month or $290/year, cancel any time.
Put your name and price on it in two minutes
The generator opens with the hvac line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.
Other trade templates
- Electrical change order templateCircuits, panel capacity, and who patches the wall afterwards.
- Plumbing change order templateConcealed pipe, stub-outs, and the wall you have to open.
- Kitchen remodel change order templateAllowances, appliances, and the layout the client changed.
- Bathroom remodel change order templateWet subfloor, niches and benches, and code-triggered work.
- Tile change order templateSubstrate, pattern, waste, and the prep under the tile.
- Roofing change order templateDecking, flashing, ice barrier, and the second layer.
- General contractor change order templateAllowances, hidden conditions, and the selections that moved.
- Painting change order templatePrep, extra coats, colour changes, and lead-safe work.
- Drywall change order templateFinish levels, texture matches, and what is behind the board.
- Free change order generatorAll nine trade templates, line items, markup and a PDF.