Change order form
Contractor change order form
A contractor change order form is the page that turns “the homeowner said yes on site” into a price, a date and a signature. Below is what the form has to contain, and the blank one you can fill in and download as a PDF — no login, no email, and nothing you type leaves your browser.
Free, no login, and the PDF is yours to keep. Sending it to the client for an e-signature is $29/month.
What the form has to contain
A form with these six things on it settles the argument at final invoice. A form missing any one of them hands the client a reason to reopen the price.
- The change, described in quantities
- Not “extras”, not “additional work”. A count, a measurement, a location: six recessed lights over the sink run, 42 linear feet of new line set, a 12 foot opening between the kitchen and the dining room.
- Why it changed, and who asked
- Owner request on 14 April, an inspector's correction, a wall that came open. The trigger and the date are what separate an approved change from a cost overrun in the client's memory.
- A price built from line items
- Quantity, unit, unit price, and markup as its own column. One lump sum invites a counter-offer on the whole number; itemised rows invite a question about one row.
- The effect on the schedule
- Which date moves and by how many working days. A change order that quietly slips the handover is the one that costs the relationship, even when the money was fair.
- A signature and a date
- Printed name, signature, date — from everyone on the contract. The date fixes when the price was agreed and when the clock on the extra work started.
- A line referencing the original contract
- One sentence saying this change order amends the signed scope of work and that the rest of the contract stands. That is what makes it an amendment rather than a suggestion.
Download a blank one
The blank form is the generator. Open it, type your business name and the line items, check the preview, and download a real one-page PDF with your name on it — no watermark, no account, no email. It is the same document the paid plans send; only the sending is paid.
- Nine trade templates, from general remodeling to HVAC, that preload the line items a trade actually bills.
- Unlimited line items with a quantity, a unit, a unit price and a markup column, and totals that update as you type.
- A reason-for-change note and a signature block, so the PDF is complete when it leaves your hands.
- Everything stays in your browser. Nothing is uploaded and nothing is emailed.
Form, template or guide?
Three different things, and it is worth knowing which one you need. A form is the blank page — this one, filled in through the generator. A template is the same page with the line items a specific trade bills, already in it: see the construction change order template or start from a trade such as electrical or roofing. A guide explains the judgement calls — how to write a change order and how change order markup works.
- Electrical change order templateCircuits, panel capacity, and who patches the wall afterwards.
- Plumbing change order templateConcealed pipe, stub-outs, and the wall you have to open.
- Kitchen remodel change order templateAllowances, appliances, and the layout the client changed.
- Bathroom remodel change order templateWet subfloor, niches and benches, and code-triggered work.
- Tile change order templateSubstrate, pattern, waste, and the prep under the tile.
- Roofing change order templateDecking, flashing, ice barrier, and the second layer.
- HVAC change order templateSizing, line sets, and the duct that cannot carry the air.
- General contractor change order templateAllowances, hidden conditions, and the selections that moved.
- Painting change order templatePrep, extra coats, colour changes, and lead-safe work.
- Drywall change order templateFinish levels, texture matches, and what is behind the board.
Free to fill in, $29 a month to send
The form and the PDF cost nothing, with or without an account, and a free account saves your orders so you can come back to them. What is paid is the moment the order leaves your hands: sending it to the client's phone, their e-signature with a timestamp, the signed PDF and photo attachments. That is Pro, at $29/month or $290/year, and it is the only thing on the site that costs money.
Fill one in now, before the crew picks the tool back up
The generator opens with a general remodeling template already loaded. Edit the lines, add the reason, download the PDF, and hand it over before the extra work starts.