General contractor change order template

A general contractor's change order has one job: turn a conversation on site into a priced, dated amendment to the contract the client already signed. This page covers the fields that make it hold up months later, with a worked example. The generator is free and needs no login — pick General remodeling, edit the lines and download the PDF.

No login, no email. The general remodeling template is preloaded and the PDF is yours to keep.

What a general remodeling change order must contain

These are the parts that decide whether the document settles an argument or starts one.

The change in the client's words, with a location
Widen the opening between the kitchen and the dining room, add a closet under the stairs, move the laundry upstairs. Room, wall, size, in the words they used when they asked. “Some framing changes” is the sentence that starts the argument at final invoice.
Whether it was a request, a condition or a code requirement
Owner request on 14 April, rot found when the floor came up, an inspector's correction notice. Name the trigger and the date it came up. That single line is what separates an approved change from a cost overrun in the client's mind.
Line items with quantity, unit price and markup
Each piece of work its own row: framing, drywall, the electrical moved out of the wall, the engineer's review. A lump sum for “additional framing” invites a counter-offer on the whole number; itemised rows invite a question about one row, which is much cheaper.
Allowances: what was included and what was chosen
If the contract carried a $4,000 tile allowance and the client chose $6,800 of tile, that is an allowance overrun, not a change order. Say which document this is, because mixing the two lets the client argue that the allowance already covered the change.
The schedule effect, in working days
Which date moves, by how many working days, and what waits on what. A change order that quietly slips the handover date is the one that costs you the relationship, even when the money on it was fair.
Approval, date, and the amendment sentence
Printed name, signature and date for everyone who is on the contract, plus one line saying this amends the signed scope of work and that the rest of the contract stands. That sentence is what makes the document an amendment rather than a suggestion.

The general remodeling traps that cost you money

The verbal yes from one of two owners
Two names on the contract, one of them says yes in the kitchen while the other is at work. Get both signatures, or write on the document who approved it and when. A change order signed by one of two owners is the one that gets argued about at the end of the job.
A change that is really an allowance overrun
They look the same on site and they are different documents. Reconcile the allowance on its own sheet with its own number, then price genuine added scope on the change order. Mixing them gives the client a way to argue that the change was already paid for.
Selections that arrive after the work was built
A vanity that lands after the plumbing rough-in was set out to the old size is rework, not a change, and it needs pricing either way. Name the date the selection changed so it is clear what caused the rework and who carries it.
Owner-supplied material
If the client buys the tile, the faucet or the doors, say in writing who carries quantities, damage and delay, and that installing their material does not make you responsible for it. The conversation is free now and expensive later.

Where this crosses another trade

A general remodeling change often drags work from another trade onto the same order. When it does, the other page covers what that half of the document has to say: kitchen remodel change order template and painting change order template.

A filled-in general remodeling change order

Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.

Change order

Sample Renovation Co.

Sample document — illustrative figures

Order
CO-001
Date
Apr 21, 2026
Client
Homeowners — whole-home remodel
Project
418 Ridgeview Dr
ItemQtyUnit priceTotal
Remove 12 lf wall between kitchen and dining room, install LVL header and posts1 ea$1,450.00$1,624.00
Reframe and patch ceiling at removed wall, ready for paint1 ea$480.00$528.00
Relocate two switch legs and add receptacle on the new dining room wall1 ea$260.00$299.00
Structural review by engineer, pass-through at cost1 ea$350.00$350.00
Subtotal
$2,540.00
Markup
$261.00
Total due
$2,801.00

Reason for the change

The owners asked on 14 April to open the kitchen to the dining room. The wall was drawn as non-bearing on the plan, and the engineer's review confirmed it can carry the load only with a new header, so the change is the header, the framing, the electrical moved out of the removed wall, and the review itself.

Effect on schedule

Two working days for the framing and the inspection, one for the patch and sand. The cabinet install moves by three working days; nothing else on the schedule changes.

Client signature

Printed name

Date

Contractor signature

Printed name

Date

Start from this template

When to issue one

  • The owner asks for scope that was not in the signed contract, and the price of it is not trivial.
  • Demo opens a wall, a floor or a ceiling and the condition behind it was never assumed by the contract.
  • A selection arrives after the work was built to the previous one, so there is rework to price.
  • An inspector requires work that nobody priced, and the correction has a cost and a date.

Questions contractors ask

Is an allowance overrun a change order?
No. An allowance is money already in the contract for a selection the client had not made yet; when the choice costs more than the allowance, the difference is an allowance reconciliation, not added scope. Keep it a separate document with its own number, and use the change order for work that was never in the contract at all.
Does a change order need both owners' signatures?
If both are on the contract, get both, or record on the document which one approved it and when. It is the difference between a change order and a conversation one of them did not hear.
Is this general contractor change order template free?
It is free and needs no login. Fill it in, check the preview and download the PDF. Nothing you type leaves your browser. Sending it to the client for e-signature is the paid part — $29/month or $290/year, cancel any time.

Put your name and price on it in two minutes

The generator opens with the general remodeling line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.