The approval block is the only part of a change order that does any work. Everything above it explains the change; the approval is what turns the explanation into an agreed price you can collect. This page sets out what has to be in that block, who has to sign it, and the four ways an approval ends up worth nothing — plus the free form you can build and download, no login required.

Free, no login, and the PDF is yours to keep. Sending it to the client for an e-signature is $29/month.

What the approval block has to contain

Five things. A form missing any one of them is an acknowledgement that the client saw something, not an approval of a price.

The exact amount, on the same page as the signature
Not “as discussed”, not “approximately”. The signature has to sit under a number, or the client is agreeing to a scope with no price and the price becomes a negotiation afterwards. If the amount is a range, write the range and the condition that picks the end of it.
The scope, in quantities and locations
What is being approved, described so a stranger could check it: 96 sq ft of drywall at the hall ceiling, one 20A circuit to the island, a 12 lf opening with an LVL header. The approval applies to what is written above it, so vague wording approves very little.
Who is approving, by printed name
A signature alone is hard to attribute months later. Printed name, and the capacity if it is not the owner themselves — “owner”, “agent for the owner”, “property manager”. That line is what stops a signature being disowned.
The date, filled in at signing
The date is what proves the price was agreed before the extra work started. Without it, the document shows that something was agreed at some point, which is the weakest possible version of the fact you need.
A sentence saying what the approval does to the contract
“This change order amends the signed scope of work dated 3 March 2026. All other terms of the contract remain unchanged.” That one sentence is what makes the page an amendment rather than a suggestion, and it is the line most home-made forms leave out.

Approval is not acknowledgement

A form that says “I acknowledge the above” records that the client read something. It does not record that they agreed to pay for it. On a job that ends up in a dispute, the difference between “I was told” and “I approved at this price” is the whole case, and it is one word on the page.

Acknowledgement

  • “Client has been informed of the additional work.”
  • Signs for receipt, not for a number.
  • Leaves the price open — and open is where it gets argued.
  • Useful for a notice, useless as an approval.

Approval

  • “Client approves the change described above at the total shown.”
  • Signs under a price, with a date.
  • Amends the contract by one sentence.
  • This is the version you can collect on.

Who signs

  • Everyone named on the contract. Two owners on the contract means two signatures, or a line on the document recording which one approved it, when, and that they were authorised to. One signature from a couple is the single most common way an approval is reopened.
  • The person with authority, not the person who is home. A tenant, a house-sitter, an adult child or a designer can agree to anything they like and bind nobody. If the decision-maker is not there, send it to them and wait — the delay is cheaper than the argument.
  • On a commercial or tenant-improvement job, whoever the lease says approves alterations. A facilities contact authorising a task is not the same as a landlord consenting to a change in the premises, and those are two different documents.
  • You as well, with a date. A countersignature costs nothing and makes the page a two-sided agreement rather than a notice you handed over.

Four ways an approval ends up worth nothing

The verbal yes
“Go ahead, I'll sign it later.” The work starts, the client's memory of the number softens, and by final invoice the conversation is about what was fair rather than what was agreed. If you have to start before the signature, send the document the same day and write on it when the go-ahead was given verbally.
The text message
A message is evidence, and weak evidence: no price, no scope, no date, and easy to characterise as a question. It is better than nothing and worse than a form, and it takes about the same amount of the client's time to send either.
The signature without the number
A page with a signature line and a blank price field is worse than no page, because it looks like an approval and proves an acknowledgement. Never send one out with the total empty, even when the price is still moving — wait, or write the range.
The approval that arrives after the work
Once the extra work is in, the client is confirming a decision that has already cost them money and has nothing left to weigh. Some will sign; the ones who will not are the ones you needed. The value of the form is entirely in getting it signed before the crew starts.

The free approval form

The free change order generator carries the approval block on every order it produces: client signature, printed name and date, a contractor signature beside it, and the line that amends the signed scope of work. Fill it in, check the preview, and download a one-page PDF with no watermark, no login and no email. Nothing you type leaves your browser.

If the change is trade-specific, start from that trade's page — drywall, electrical, tile — and the line items arrive already shaped for the work, with the same approval block underneath.

Free to build, $29 a month to send for signature

Building the form and downloading the PDF costs nothing, with or without an account, and a free account saves your orders. What is paid is sending it: the client opens it on their phone, signs it, and the timestamped record and signed PDF are kept for you — $29/month or $290/year. Nothing else on the site costs money.

For the rest of the document around the approval block, read a filled-in change order example and how to write a change order.

Get the signature before the work starts

Open the generator with a general remodeling template loaded, add the lines and the price, and download the PDF with the approval block on it.