Example

Change order example

A change order example that shows the whole document: who it is from, what changed, what it costs line by line, why it changed, which dates move, and where the client signs. The figures below are illustrative and priced for one job — they are not a price list, and the point of the example is the shape of the document, not the numbers in it.

Free, no login, and the PDF is yours to keep. Sending it to the client for an e-signature is $29/month.

The filled-in example

One change, priced: a wall opened between a kitchen and a dining room after the contract was signed, with the framing, the electrical that had to move, and the engineer's review that made the header necessary.

Change order

Sample Renovation Co.

Sample document — illustrative figures

Order
CO-001
Date
Apr 21, 2026
Client
Homeowners — whole-home remodel
Project
418 Ridgeview Dr
ItemQtyUnit priceTotal
Remove 12 lf wall between kitchen and dining room, install LVL header and posts1 ea$1,450.00$1,624.00
Reframe and patch ceiling at removed wall, ready for paint1 ea$480.00$528.00
Relocate two switch legs and add receptacle on the new dining room wall1 ea$260.00$299.00
Structural review by engineer, pass-through at cost1 ea$350.00$350.00
Subtotal
$2,540.00
Markup
$261.00
Total due
$2,801.00

Reason for the change

The owners asked on 14 April to open the kitchen to the dining room. The wall was drawn as non-bearing on the plan, and the engineer's review confirmed it can carry the load only with a new header, so the change is the header, the framing, the electrical moved out of the removed wall, and the review itself.

Effect on schedule

Two working days for the framing and the inspection, one for the patch and sand. The cabinet install moves by three working days; nothing else on the schedule changes.

Client signature

Printed name

Date

Contractor signature

Printed name

Date

The same example is what the free generator opens with when you pick General remodeling. Change the numbers, the client and the reason, and the PDF is yours.

What each block in it is doing

Header: business, order number, date, client, project
The order number is what lets you talk about “CO-001” three months later instead of describing a conversation. The date fixes when the price was offered; the project address stops the document being applied to the wrong job when a client has more than one.
Line items with quantity, unit, unit price and markup
Four rows instead of one lump sum. A lump sum invites a counter-offer on the whole number; four rows invite a question about one row, and answering one row is a much cheaper conversation than defending the total.
Subtotal, markup and total as three separate numbers
The client can see that the markup is a line and not a hidden margin inside each price. The engineer's review sits at zero markup because it is a pass-through, and saying so buys credibility for the rows that are not.
Reason for the change, dated
“The owners asked on 14 April” plus the fact that made it more expensive than the plan suggested. This paragraph is the difference between a documented change and an invoice the client reads as a surprise.
Effect on the schedule, in working days
Which date moves and by how much. The money on a change order is arguable; a handover date that quietly slipped is what damages the relationship, so it goes on the same sheet as the price.
Two signature blocks with printed name and date
One for the client, one for you. The client's date is the evidence that the price was agreed before the work started, which is the only thing this document exists to prove.

The same change, written two ways

Almost every change order that fails does so in the description, not the arithmetic. These are the same two rows before and after they are written properly.

Written badly

Framing changes — $1,930

Written so it holds

Remove 12 lf of non-bearing wall between kitchen and dining room, install LVL header and posts, reframe and patch ceiling — 1 ea @ $1,450 with 12% markup, plus $480 to reframe and patch the ceiling

Written badly

Electrical extras

Written so it holds

Relocate two switch legs out of the removed wall and add one receptacle on the new dining room wall — 1 ea @ $260 with 15% markup

Written badly

Engineer

Written so it holds

Structural review by engineer to confirm the header size, billed at cost with no markup — 1 ea @ $350

The weak version is not dishonest, it is just unusable: a month later nobody can check what was in it. The strong version can be checked by the client, by you, and by anyone else who has to read the job file.

What an example cannot give you

Your own unit prices. Every number in the document above belongs to a made-up job in a made-up town, and copying them onto a real change order is how contractors end up working for nothing. The structure travels; the prices do not. The same goes for markup: there is no correct percentage, only the one that covers your overhead on that job, and it is a number only you can put in.

If you want a version already shaped for a trade, start from general contracting, drywall or kitchen remodels. For the judgement calls behind the document, read how to write a change order, and for the approval half of the page see the change order approval form.

Free to build, $29 a month to send

The generator, the line items, the markup column, the live totals and the one-page PDF are free and need no login. Sending the finished order to the client for an e-signature, with the timestamp and the signed PDF kept as your record, is Pro at $29/month or $290/year. A free account saves your orders so you can come back to them.

Write yours from this shape

Open the generator with a general remodeling template already loaded, replace the sample lines with your own work, and download the PDF before the crew starts.