Comparison
Change order vs variation order
A change order and a variation order are the same document under two names: “change order” is the usual term in the United States, “variation” in the UK, Ireland, Australia and New Zealand, and the two are used interchangeably in most contracts that get argued about. A work order is not the same thing at all, and the difference is worth knowing before you sign one. This page covers both comparisons, and the generator behind it is free and needs no login.
Free, no login, and the PDF is yours to keep. Sending it to the client for an e-signature is $29/month.
Change order or variation order: the same document
If you are writing for a UK or Irish client, or working under a JCT-style contract, the word on your document should be variation or variation order. In the US it is a change order. Nothing else changes: a description of the work, a price, the effect on the schedule, the client's approval and a date.
The reason to use the client's word is not politeness. If the contract says the price may only be changed by a written variation instructed by the contract administrator, a document headed “change order” is an easier thing for a payer to set aside. Match the contract's language and you remove that argument before it starts.
| Term | Where it is used | What it does |
|---|---|---|
| Change order | US residential and commercial work | Amends the signed contract price and scope |
| Variation / variation order | UK, Ireland, Australia, New Zealand | The same amendment, under the contract's own word |
| Work order | Service calls, maintenance, tenant work | Authorises a task; usually does not amend a contract |
| Purchase order | Suppliers and subs buying material | Orders goods at a price; not an approval of scope |
Where the two names actually differ
- The contract's own language governs
- Whichever word your contract uses, use that one on the document. A change order issued under a contract that only contemplates variations is a document the other side can argue about on a technicality, and technicalities are cheap to raise and expensive to answer.
- Who may instruct the change
- On larger UK work the contract administrator or employer's agent issues the instruction, and a variation agreed directly with the person on site may not bind anyone. On a US residential job the owner signs. Either way, the person who signs has to be the person entitled to sign, or the paper proves nothing.
- Notice periods and valuation rules
- Some contracts require a variation to be notified within a set number of days, and some set out how it is valued — dayworks, rates in a schedule, or a quoted price. Those rules are in your contract, not in this page, and they decide whether your number is the number. Read the clause before you price the work.
- The words on the page are nearly identical
- Description, quantities, price, schedule effect, signature, date. A variation order with those six things does the same job as a change order with those six things. The document is the same; the vocabulary around it is not.
Change order vs work order: not the same thing
A work order is a document that authorises a task. It says what to do and where, and it is the right paper for a service call, a warranty visit, a maintenance item or a small repair that the client is paying for on its own. What it usually does not do is amend the contract that is already signed — the price for the project, the scope in it and the completion date all stay exactly where they were.
That is the whole difference, and it matters in one direction: added scope that belongs in the contract has to go on a change order, not a work order. When a client signs a work order for “extra framing”, the project contract still says the framing was included, and the argument at final invoice is about whether the work order was a variation of the contract or a separate little job you were paid for once. A change order answers that question in one sentence; a work order leaves it open.
Use a change order when
- The work was not in the signed scope and it changes the contract price.
- A condition found after demo has to be paid for before it is fixed.
- The completion date moves because of the client's choice.
- The client is on a contract you both signed and you want it amended, not replaced.
Use a work order when
- It is a service call, a repair or a maintenance visit billed on its own.
- There is no continuing contract for it to amend.
- A property manager or facilities contact is authorising a task for a tenant.
- The work is a small job at a separate address with its own price.
The mistakes that come from mixing the two
- Calling added scope a work order because the work order template was already open. The client pays once, and the contract still says the work was included, so the next argument is about a refund rather than a bill.
- Issuing a change order for a warranty repair. That tells the client their warranty does not exist, and it is a claim you invented against yourself.
- A variation order with no price on it, “to be agreed”. It records that the work happened and nothing about what it costs, which is the version that gets valued by the other side's rules rather than yours.
- Two documents for one change — a work order for the crew and a change order for the client, with different numbers on them. Keep one document, or make the second reference the first by number.
Build either one in the same place
The free change order generator produces the document either way: line items with quantities and unit prices, a markup column, live totals, a reason-for-change note, the schedule effect and a signature block. Pick a trade — general contracting, electrical, plumbing — and the line items arrive already shaped for that work. If your contract says “variation”, change the heading and the word in the body text; the fields are the same.
For the parts that decide whether the document holds up, see the change order approval form, a filled-in change order example, and how to write a change order.
Free to build, $29 a month to send
The document and the PDF are free, with no login and no email, and a free account saves your orders. Sending the finished order to the client's phone for an e-signature — with the timestamp, the signed PDF and photo attachments kept as your record — is Pro at $29/month or $290/year.
Put the client's word on it
Open the generator, describe the change in the language your contract uses, price it line by line and download the PDF before the work starts.